Past exam question: 2081 Chaitra (Regular), Q6(a)

Communication English · 5 marks

Open in the Padhaiko app

Topic: Tables, Graphs, Charts & Diagrams

Question

Create a bar graph to show the work schedule of any proposed work.

Solution

Bar Graphs in Engineering Work Scheduling (Gantt Charts): In engineering project proposals, a horizontal bar graph—widely known as a Gantt Chart—is the standard visual tool for scheduling and tracking project activities. The vertical axis lists the sequential and concurrent work tasks comprising the project breakdown structure, while the horizontal axis represents the project timeline divided into chronological units (weeks or months). The horizontal span of each bar illustrates the task's start date, duration, and completion deadline.

Proposed Engineering Work Scenario: Solar Micro-Grid Power Project: Consider a 12-week proposed engineering installation: "Design, Procurement, and Commissioning of a 15 kW Solar Micro-Grid System for a Rural Health Facility". The work is divided into five core task phases:

  1. Site Topographical & Solar Radiation Survey (Weeks 1–2)
  2. Foundation Civil Works & Battery Room Construction (Weeks 2–5)
  3. Equipment Procurement & Logistics Dispatch (Weeks 3–7)
  4. Solar PV Array Mounting & Inverter Electrical Wiring (Weeks 6–10)
  5. System Testing, Grid Synchronization & Staff Training (Weeks 10–12)

Work Schedule Bar Graph (Gantt Chart Visualization):

Proposed Task PhaseDurationW01W02W03W04W05W06W07W08W09W10W11W12
1. Site Survey & System DesignWk 1–2[======]
2. Foundation & Battery Room Civil WorksWk 2–5[============]
3. Hardware Procurement & TransportWk 3–7[===============]
4. PV Array Mounting & Electrical WiringWk 6–10[===============]
5. System Calibration & TrainingWk 10–12[=========]

Legend: [=== ===] indicates active execution of the project activity. The horizontal overlap shows concurrent task progression (e.g., equipment procurement commences while civil construction is underway).

Project Management Insights from the Bar Graph:

Answer:

The horizontal bar graph (Gantt chart) outlines a 12-week engineering schedule for a solar micro-grid installation across five distinct phases (Survey/Design, Civil Construction, Procurement, Electrical Mounting, and Calibration/Training). The horizontal bars visually depict task durations, concurrent operations, and critical project dependencies.