Past exam question: 2081 Chaitra (Regular), Q6(a)
Open in the Padhaiko appCreate a bar graph to show the work schedule of any proposed work.
Solution
Bar Graphs in Engineering Work Scheduling (Gantt Charts): In engineering project proposals, a horizontal bar graph—widely known as a Gantt Chart—is the standard visual tool for scheduling and tracking project activities. The vertical axis lists the sequential and concurrent work tasks comprising the project breakdown structure, while the horizontal axis represents the project timeline divided into chronological units (weeks or months). The horizontal span of each bar illustrates the task's start date, duration, and completion deadline.
Proposed Engineering Work Scenario: Solar Micro-Grid Power Project: Consider a 12-week proposed engineering installation: "Design, Procurement, and Commissioning of a 15 kW Solar Micro-Grid System for a Rural Health Facility". The work is divided into five core task phases:
- Site Topographical & Solar Radiation Survey (Weeks 1–2)
- Foundation Civil Works & Battery Room Construction (Weeks 2–5)
- Equipment Procurement & Logistics Dispatch (Weeks 3–7)
- Solar PV Array Mounting & Inverter Electrical Wiring (Weeks 6–10)
- System Testing, Grid Synchronization & Staff Training (Weeks 10–12)
Work Schedule Bar Graph (Gantt Chart Visualization):
| Proposed Task Phase | Duration | W01 | W02 | W03 | W04 | W05 | W06 | W07 | W08 | W09 | W10 | W11 | W12 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. Site Survey & System Design | Wk 1–2 | [=== | ===] | ||||||||||
| 2. Foundation & Battery Room Civil Works | Wk 2–5 | [=== | === | === | ===] | ||||||||
| 3. Hardware Procurement & Transport | Wk 3–7 | [=== | === | === | === | ===] | |||||||
| 4. PV Array Mounting & Electrical Wiring | Wk 6–10 | [=== | === | === | === | ===] | |||||||
| 5. System Calibration & Training | Wk 10–12 | [=== | === | ===] |
Legend: [=== ===] indicates active execution of the project activity. The horizontal overlap shows concurrent task progression (e.g., equipment procurement commences while civil construction is underway).
Project Management Insights from the Bar Graph:
- Sequence and Dependencies: Mounting and Electrical Wiring (Phase 4) cannot commence until both Civil Foundations (Phase 2) and Equipment Delivery (Phase 3) reach completion in Week 6.
- Concurrent Execution: Hardware procurement runs parallel with foundation construction between Weeks 3 and 5, shortening the overall project delivery timeline.
- Critical Milestones: Commissioning and Staff Training (Phase 5) represents the terminal project milestone, enabling smooth administrative handover at the end of Week 12.
The horizontal bar graph (Gantt chart) outlines a 12-week engineering schedule for a solar micro-grid installation across five distinct phases (Survey/Design, Civil Construction, Procurement, Electrical Mounting, and Calibration/Training). The horizontal bars visually depict task durations, concurrent operations, and critical project dependencies.