Past exam question: 2082 Kartik (Back), Q6(a)

Communication English · 5 marks

Open in the Padhaiko app

Topic: Tables, Graphs, Charts & Diagrams

Question

Create a bar graph to show the work schedule of any proposed work.

Solution

Concept and Role of Bar Graphs in Project Work Schedules: In engineering proposals and project management, work schedules are illustrated using horizontal bar graphs, commonly referred to as Gantt Charts. A work schedule bar graph plots scheduled activities along the vertical axis (Y-axis) and project timeline increments (weeks or months) along the horizontal axis (X-axis). The length of each horizontal bar depicts the planned duration of that activity, immediately displaying task sequences, overlapping phases, and milestone dependencies.

Proposed Project Case: Software Engineering Project (Campus ERP Development): Consider a 16-week software engineering project entitled "Development and Deployment of an Integrated Campus Management Information System (MIS)", segmented into six sequential and concurrent tasks:

  1. Requirements Analysis & Feasibility Study (Weeks 1–3)
  2. System Architecture & UI/UX Design (Weeks 3–6)
  3. Backend & Database Module Development (Weeks 5–11)
  4. Frontend Interface Integration (Weeks 8–13)
  5. Quality Assurance, Security & Load Testing (Weeks 11–15)
  6. User Acceptance Testing (UAT) & Cloud Deployment (Weeks 14–16)

Horizontal Bar Graph (Gantt Chart Work Schedule):

Task ActivityPlanned DurationW01W02W03W04W05W06W07W08W09W10W11W12W13W14W15W16
1. Requirements & FeasibilityWk 1–3[=========]
2. Architecture & UI DesignWk 3–6[============]
3. Backend & DB DevelopmentWk 5–11[=====================]
4. Frontend IntegrationWk 8–13[==================]
5. QA & Security TestingWk 11–15[===============]
6. UAT & Final DeploymentWk 14–16[=========]

Legend: [=== ===] indicates active execution period of the scheduled task. Overlapping bars illustrate concurrent task execution (e.g., frontend integration progressing alongside backend development).

Key Elements Illustrated by the Bar Graph:

Answer:

The horizontal bar graph (Gantt chart) maps a 16-week software engineering project schedule across six sequential and concurrent tasks (Requirements, Architecture/UI Design, Backend Development, Frontend Integration, QA Testing, and Final Deployment). The horizontal bars visually denote task start dates, active durations, parallel execution phases, and project delivery milestones.